CAMAC Progress Report Week Ending: June 22, 2001 Week: 21 Tom Folkers: 1. Helping Tom and Pete with encoder ADC/DSP hardware. 2. More work on pending move to the first floor. 3. Received the recently repaired BSI computer back from repairs and reinstalled Linux 7.1 Tom Sargent: Pete Hubbard: 1. A/D testing and temporary power supply fix. The current requirements were not proper for the boards. 2. Finding the proper way to sample data with the clock. Turns out sample clock had to be a pulse of at least 150 ns and no longer then 64 times master clock = 10ms. 3. Ready encoder and amp board for A/D testing. Dave Ashby: 1. No Report.