| Job # |
Done? |
Category |
Job/Description |
Who ? |
Priority |
| |
|
|
|
|
|
| Buliding: |
|
|
|
|
|
| 1 |
NOT |
Mech |
Man lift for door seals |
Steve |
1 |
| 2 |
Working |
Mech |
Roof & door seals |
Steve |
1 |
| 3 |
|
Mech |
Seal door on 5th floor |
Steve |
1 |
| 4 |
Working |
Mech |
Widen door between receiver rooms |
Steve |
1 |
| 5 |
|
Mech |
Install hatch in receiver room |
Steve |
1 |
| 6 |
Done |
Mech |
Seal vents |
Steve |
1 |
| 7 |
|
Mech |
Install taumeter cover |
Steve |
1 |
| 8 |
Done |
Mech |
Fireproof building |
Steve |
2 |
| 9 |
|
Maint |
Reinstall drywall |
Steve |
2 |
| 10 |
Done |
Mech |
Fix rubbing hydro cylinder |
Steve |
2 |
| 11 |
|
Maint |
Paint fourth floor |
Steve |
3 |
| 12 |
Done |
Mech |
Hydraulic service |
Steve |
1 |
| 13 |
Done |
Maint |
Clean track. |
All |
1 |
| 14 |
|
Mech |
Adjust building wheels |
Steve |
1 |
| 15 |
|
Maint |
Crane maintenance |
Steve/Harry |
1 |
| 16 |
|
Mech/Elec |
Fans in 5th floor walls |
Steve |
2 |
| 17 |
|
Mech/Elec |
Building drive tests |
Harry et al |
2 |
| 18 |
|
Electrical |
Heat tape checks and mods |
Harry |
2 |
| 19 |
|
Electrical |
UPS to 5th floor |
Harry |
2 |
| 20 |
Done |
Electrical |
Install light in chiller room |
Steve |
3 |
| 21 |
|
Electrical |
Door and roof limit switches |
Steve/Harry |
1 |
| 22 |
|
Electrical |
Install new weather station |
Steve |
2 |
| 23 |
|
Electronic |
Building drive current signals-
find noise source. |
Pete |
1 |
| 24 |
|
Electronic |
Check for Building ground loop's. |
Pete |
1 |
| 25 |
|
Program |
Measure (& log?) building currents. |
Pete/Tom |
2 |
| |
|
|
|
|
|
| Telescope: |
|
|
|
|
|
| 26 |
Done |
Mech |
Inspect and grease hot-vane slider. |
Steve et al |
1 |
| 27 |
|
Mech |
Calibrate building vs antenna limit
switches.. |
Steve/Harry |
1 |
| 28 |
|
Electrical |
Rewire Krupp for LED's. |
? |
1 |
| 29 |
|
Mech |
Check elevation wrap |
Steve |
1 |
| 30 |
|
Program |
Check out inclinometers. |
Bill/Pete |
2 |
| 31 |
|
Electronic |
Inclinometer low pass filter -PCB
and hook up temp sensor. |
Pete |
1 |
| |
|
|
|
|
|
| Peir: |
|
|
|
|
|
| 32 |
Done |
Mech |
Clean and grease Az and El bearings |
Steve et al |
1 |
| 33 |
|
Mech |
Clean & grease ring gear |
Steve |
1 |
| 34 |
|
Mech |
Grease elevation motors |
Steve |
1 |
| 35 |
|
Mech |
Check Az wrap for cable wear. |
Steve |
2 |
| |
|
|
|
|
|
| Control System: |
|
|
|
|
|
| 36 |
Done |
Admin |
Back up all observers data / user
areas |
Tom |
1 |
| 37 |
Working |
Admin |
Upgrade all Non-Realtime Linux
boxes to RH7.3 |
Tom |
1 |
| 38 |
Working |
Admin |
Get all Linux boxes on RHN |
Tom |
1 |
| 39 |
Done |
Admin |
Install firewall |
Tom |
1 |
| 40 |
Done |
Admin |
Identify any bad scsi disks on tux
and replace or repair. |
Tom |
1 |
| 41 |
Done |
Admin |
Find a permanent home for smtotux |
Tom |
2 |
| 42 |
Working |
Program |
Clean up CACTUS_GLOBAL. |
Tom |
1 |
| 43 |
|
Program |
Install receiver fuctions in global
memory. |
Tom |
1 |
| 44 |
|
Program |
Install and program zero check box
on VCO's |
Pete/Tom |
1 |
| 45 |
Started |
Program |
Finish IF routing and software on
FMS |
Pete/Tom |
1 |
| 46 |
Working |
Program |
Order and install new FMS mother
board |
Tom |
1 |
| 47 |
|
Program |
Finish 'goodness of fix' function
in five points. |
Tom |
2 |
| 48 |
|
Program |
We need an 'Ignore Offsets' button
in Rambo Spec 5 screen |
Tom |
1 |
| 49 |
|
Program |
Allow accepting individual channels
in fits. |
Tom |
2 |
| 50 |
|
Program |
Rambo should indicate it's taking
data. |
Tom |
2 |
| 51 |
|
Program |
Line name into headers |
Tom |
1 |
| 52 |
|
Program |
Spec 5 offsets are not in class
files. |
Tom |
1 |
| 53 |
|
Program |
Inproper beams alarm. |
Tom |
1 |
| 54 |
|
Program |
Fix Tipper going below tree line? |
Tom |
2 |
| 55 |
|
Program |
Put final touches on remote
observing package. |
Tom |
2 |
| 56 |
|
Admin |
Finish remote observing document |
Tom |
2 |
| 57 |
Done |
Program |
Port UPSsuck, WeatherSuck, and
WindSuck. |
Bill |
1 |
| 58 |
|
Program |
Port Tipsuck. |
Bill |
1 |
| 59 |
|
Program |
Port FitIncRealtime |
Bill |
1 |
| 60 |
Done |
Admin |
Download the terminal servers from
Linux. |
Bill |
1 |
| 61 |
|
Program |
Log sun distance and angle. |
Tom |
2 |
| 62 |
Done? |
Program |
SAMBUS channels 27-31 (+ ...) don't
work. |
Bill/Pete |
2 |
| 63 |
Done |
Program |
What about spontaneous 0x80 bit? |
Bill/Pete |
2 |
| 64 |
---- |
Program |
Get latching mode to work in
VxWorks 0-15 |
Bill/Pete |
2 |
| 65 |
Done |
Admin |
Turn on Linux xdm server for
X-terminals. |
Bill |
2 |
| 66 |
|
Program |
Remember focus & pointing settings
between receiver changes. |
Tom |
1 |
| 67 |
|
Program |
Clean out unneeded log messages,
especially msg's to Monitor. |
Tom/Bill |
2 |
| 68 |
|
Program |
Log encoder fit parameters vs
angle. |
Tom S/Tom |
2 |
| 69 |
|
Program |
Log encoder zero point resets and
fiducial encounters w/o reset. |
Tom S./Tom |
2 |
| 70 |
|
Program |
Make successive tracker polynomials
join at the ends. |
Tom S. /Bill |
1 |
| 71 |
|
Program |
Check out tracking at high
elevation and high speed (holo) |
Tom S. /Bill |
1 |
| 72 |
|
Program |
Make servo work with both elevation
encoders. |
Tom S. |
1 |
| 73 |
|
Program |
More Testing of Sun Avoidance. |
Tom S. |
1 |
| 74 |
|
Program |
Servo recoverery during drive
cycling. |
Tom S. |
1 |
| 75 |
|
Program |
Port NETCHECK. |
Bill |
2 |
| 76 |
|
Program |
Install raster scanning pointing. |
Tom/Bill |
2 |
| 77 |
Working |
Program |
Configure and Install displays in
kitchen and lounge. |
Tom |
1 |
| 78 |
|
Admin |
Upgrade Autocad on mountain. |
Carlson |
2 |
| 79 |
|
Program |
Add VATT weather info to our
displays. |
Tom |
3 |
| 80 |
Done |
Program |
Clean up 'mailboxdefs' file |
Tom |
1 |
| 81 |
|
Program |
BSCAL should not be done on source. |
Tom |
1 |
| 82 |
|
Program |
Add Vane temperature to GLOBAL |
Tom |
1 |
| 83 |
Done |
Program |
Rewrite mailboxdefs file |
Tom |
2 |
| |
|
|
|
|
|
| |
|
|
|
|
|
| Prime Focus: |
|
|
|
|
|
| 84 |
|
Computing |
Install sensors on focus
translation stage and quadrapod. |
Bob S./Tom |
1 |
| 85 |
|
Computing |
Thermal test on Sub-Reflector? |
? |
2 |
| 86 |
|
Computing |
Check sun limits and for heating of
focus translation stage. |
Tom/Bill/Tom |
1 |
| 87 |
|
Computing |
Move the lower limit switch on
Focus Motor #1 0.3 mm or so. |
? |
2 |
| 88 |
|
Mech |
Subreflector Work ( remove from
telescope) |
Steve/Harry |
1 |
| 89 |
|
Maint |
Touch up paint work on quadrapod |
? |
2 |
| 90 |
|
Mech |
Optical telescope tests |
Tom |
3 |
| 91 |
|
Computing |
Pinhole camera tests |
Bill et al |
1 |
| 92 |
Working |
Computing |
Get Optical focus to work w/o
laptop. |
Tom |
1 |
| 93 |
Working |
Computing |
Get Optical pointing mode up w/o
twf. |
Tom |
1 |
| 94 |
|
Computing |
Get Optical focus stage with more
range? |
? |
2 |
| |
|
|
|
|
|
| Receivers: |
|
|
|
|
|
| 95 |
|
Receiver |
Cold Head maintenance |
Martin |
1 |
| 96 |
|
Receiver |
Compressor repairs and
modifications |
Martin |
2 |
| 97 |
|
Receiver |
Install 2mm JT receiver |
Harry |
1 |
| 98 |
|
Receiver |
Tuning tests, 345 GHz |
Harry |
2 |
| 99 |
|
Electronic |
Bias Box modifications 460 GHz |
Harry |
2 |
| 100 |
Done |
Receiver |
Change oil in vacuum pump |
Steve |
2 |
| 101 |
|
Electrical |
Install power for compressor |
Steve |
2 |
| 102 |
|
Mech |
Repair light tower limit switch. |
Pat |
1 |
| |
|
|
|
|
|
| Backends/IF: |
|
|
|
|
|
| 103 |
|
Electronic |
Filter Bank tests and repairs |
Harry |
2 |
| 104 |
|
Electronic |
Chirp Downconverter mods (2.1 GHz
IF ) |
Harry |
1 |
| 105 |
|
Electronic |
New cables for the Backend Switch
Box |
Martin |
2 |
| 106 |
Working |
Electronic |
IF back end box; Finish
instillation. |
Pete |
1 |
| 107 |
Working |
Electronic |
VCO Zero box- PCB and construction. |
Pete |
1 |
| 108 |
Working |
Electronic |
Encoder power supplies- Change to
external 115 Volts.. |
Pete |
1 |
| 109 |
Working |
Electronic |
New Encoder amplifier boards- PCB
layout and construction. |
Pete |
1 |
| |
|
|
|
|
|
| Misc: |
|
|
|
|
|
| 110 |
|
Electronic |
10 MHz Distribution noise tests |
Harry |
2 |
| 111 |
|
Electronic |
Temperature monitor for Maser Room |
Harry |
3 |
| 112 |
|
Mech |
Siding on Hilton |
Steve |
2 |
| 113 |
|
Mech |
Clean Basecamp container |
Steve |
3 |
| 114 |
|
Mech |
Purchase and install weather
station box. |
Robert |
2 |
| 115 |
Done |
Purchase |
Purchase and install new audio
system. |
Bill Hale et al |
3 |
| |
|
|
|
|
|